A project's Schedule Variance (SV) is simply the difference between the Earned Value (EV) and the Planned Value (PV). The value is positive if the budgeted cost of the work performed is greater than the budgeted cost of the work scheduled. In other words, SV is positive whether a project is ahead of schedule.
`SV=EV-PV`